Today the contractor finished the last pile for the foundation work (378 pilings complete). There is now over 90 metric tons of steel and 44,000 cubic feet of concrete in the ground to support the building. As we start to build upward the progress will start to be much more visible vs during the pilings only seeing the site get built up with sand and mud day by day. We will now have the building laid out again for the pile cap and short column work. We hope to get a good start on this work for the basement area prior to the next Eid holiday mid-October.
Jon
(Site Overview from the South - Last day all four crews were on site)
Jon