The basement slab casting was just completed over the past couple days (Jan 25th & 26th). This is an exciting milestone on the project, the first of a planned 12 major slab castings as we build upward. A lot of men put in long hard days to get this job completed.
Jon
Over 300 people on site working on this first casting day
Loading and mixing the concrete batches
Moving the concrete from the mixer to the current casting location
Jon seeing how heavy a pan is (only half a load)
Holly watching the mixing to ensure mix design is being followed
Jon moving around site ensuring proper casting
Finishing the final section of concrete on the second day
The workshop using some imported power trowels to give the surface a smoother finish
Jon
No comments:
Post a Comment