The last three footings were cast yesterday on site. This finishes a major foundation phase of the project. From now on we will be building UP. Basement slab and retaining wall work in ongoing with steel tying. Under-slab conduit and pipe work will be completed once the remaining materials become available between the continuing road strikes. Grade beam work is also expected to start within the next couple weeks on the Northeast side of the building.
Basement Slab & Retaining Wall Steel Reinforcement
Final checking then casting of the last three pile caps
Under slab conduit and pipe work
Jon