Over the past two days we were able to complete the Ground Floor casting over the basement. It took over 240 workers on site a total of 15 + 11 hours over these days. The hot season is now definitely upon us with high temperatures and humidity (39C/102F). This completes the second of a planned 12 major slab castings.
Site overview day one casting
Head loading the concrete to be placed
Completed retaining wall with slab casting ongoing above (First layer of bitumen, poly then Platon installed on exterior of wall)
Site overview on casting day two
Completed casting - preparing for ponding
Jon