Thursday, January 29, 2015

Third Floor East Wing - Poured

Over the past two days the third floor west wing has just been poured. Thankfully it was another relatively smooth work as the crews now understand our expectations and standards - along with no significant equipment failures. Only two major slab castings (both roofs) remaining on the hospital.


 Third Floor East Slab Casting - Day 2

 Third Floor Slab Casting - Day 1
East Wing Work Progress - Third Level Casting, Second Level Bracing,  First Level Brick Wall Layout, Ground Floor Brick wall progress and ceiling plaster.

Ground Floor Plaster Work (East) - Left work completed the day before, Middle ongoing work, Right tomorrow's work.

Jon Barrett

 