The East Wing Roof was cast today from 5:15am till 3:15am the next
morning (22 hours). This is the last of the large wing castings. Over
the next six weeks all the remaining structural works will be completed
with one more medium size (6,000 sq ft) and one small (2,000 sq ft)
slab.
Jon
East Wing Roof - Slab Casting - Feb 28, 2015
Site Overview - Feb 24, 2015
New Project View from Existing Hospital Entrance
Progress on the OPD waiting and Pharmacy Area
West Wing - West Elevation Progress
Jon