Monday, September 29, 2014

West Wing - Structure Complete

On Saturday (Sept 27th) the West Wing roof (4th level slab) was completed.  This is another major milestone for the project as all the shuttering will now be moved to the East Wing after Eid, at which time the exterior brick work can be started and the interior brick walls completed. Once the brick work is completed then Phase II interior finishing will start once funding for this next phase becomes available (electrical conduit, wall plaster, flooring, etc.). Structural work on the East wing will continue over the next 6 months.


Site Overview - Sept 27, 2014
West Wing Roof Casting - (4th Floor Slab)

A Sudden Thunderstorm During Casting (Construction workers taking shelter on the 2nd floor)

Jon out in the downpour

 Over 80,000 sq feet of slab casting completed

Working well into the night

Jon and Holly Barrett

Sunday, September 21, 2014

MCH - GF East/ 4th Floor West / Interior Walls


Sunset just out in front of our house in Malumghat - everything is so vivid green during the rain season

Surgery team walking through the new surgery wing to confirm layout

Surgery team in the new Surgery Wing
 
Site overview - Sept 15, 2014 - 4th slab ready for casting this week - Interior walls going up on Ground and First Floor (West Wing)

Ground Floor East Wing - Slab casting complete
 
After a couple weeks of good weather the rain has returned with great intensity over the past 10 days.

Caught out on site during a rain storm
 
Jon

Tuesday, September 02, 2014

MCH - Interior Brick Walls

The interior brick walls have started on the ground floor (West Wing) this past week. These will be built up to 7' before moving on to the first floor and so forth up the building. Once the top level is completed work will move back down completing these walls to ceiling height.
 
Starting the interior brick wall partitions
Ground Floor (West) - Surgery Clinic, Cast, PT, Radiology
 
Wall layout
 
Rains have subsided somewhat so fill work has resumed. Plumbing and filling on the North East wing will be complete this week
 
Water snake found on site (Checkered Keelback) 
A worker removing the snake from the site
 
 
Jon