The East Hospital wing is now well underway with the ground floor slab completed and the first floor slab shuttering and reinforcing work nearing completion (slab casting first of next week).
East Wing first floor shuttering and steel reinforcing work
Site overview - November 9, 2014
The OPD waiting wing ground floor casting was completed this past week.
Interior construction continues on the West Wing with ongoing brick work, lintel casting and ceiling plaster work.
Jon
OPD waiting area - slab on grade casting
OPD waiting slab casting
Interior construction continues on the West Wing with ongoing brick work, lintel casting and ceiling plaster work.
West Wing - 3rd Level - Ceiling Plaster work
Completed ceiling plaster and lintel casting
Jon